Rule303.
(1) Construction and demolition waste landfills that are existing disposal areas shall be in compliance with all of the requirements of this part that are not designated as applying to new disposal areas only.
(2) The owner and operator of an existing construction and demolition waste landfill shall comply with the final cover requirements of R 299.4304 for all units that are not certified to be closed within 6 months of the effective date of these rules and with the design requirements of R 299.4307 for any new unit or lateral extension of an existing unit.
(3) The owner and operator of an existing construction and demolition waste landfill are not required to submit revised engineering plans to the director, but shall submit as-built plans as part of the construction certification pursuant to the provisions of R 299.4921.
(4) Not later than October 9, 1994, the owner and operator of a construction and demolition waste landfill shall revise existing hydrogeologic monitoring plans as necessary to comply with R 299.4905 and shall submit such plans to the director with the first operating license application or reapplication that is made after October 9, 1994.
These administrative rules are provided as a free service
of the State Bar of Michigan Environmental Law Section. The administrative rules, which were
re-formatted for consistency, are not intended to replace official versions and
are subject to revision and/or repeal.
The Environmental Law Section presents this information, without
warranties, express or implied, regarding the accuracy of the information,
timeliness, or completeness. If you believe the information is inaccurate,
out-of-date, or incomplete or if you have problems accessing or reading the
information, please send your concerns to the Section.