Administrative Rules for
PART 115 SOLID WASTE MANAGEMENT ACT
of the Natural Resources and Environmental Protection Act 1994 PA 451, as
amended
(Effective January 6, 1982; revised October, 7, 1993)
Rule313.
(1) A verification by a registered professional engineer that the construction of a type III landfill unit was in accordance with the approved engineering plans shall accompany all license applications for newly constructed units. Construction records that are specified in R 299.4921 shall accompany the verification.
(2) An operating license application for a new unit that is upgraded to meet the requirements of these rules shall include as-built plans of the unit that are in compliance with the provisions of R 299.4910.
(3) The application package shall be submitted to the solid waste control agency.
(4) The solid waste control agency shall make at least 1 inspection of the landfill after receiving a license application and shall, before license issuance, evaluate the status of compliance with the act and these rules.
These administrative rules are provided as a free service
of the State Bar of Michigan Environmental Law Section. The administrative rules, which were
re-formatted for consistency, are not intended to replace official versions and
are subject to revision and/or repeal.
The Environmental Law Section presents this information, without
warranties, express or implied, regarding the accuracy of the information,
timeliness, or completeness. If you believe the information is inaccurate,
out-of-date, or incomplete or if you have problems accessing or reading the
information, please send your concerns to the Section.