Administrative Rules for
PART 115 SOLID WASTE MANAGEMENT ACT
of the Natural Resources and Environmental Protection Act 1994 PA 451, as amended

  Previous|Home|Chapter Contents|Next  

R 299.4313 Type III landfill licensing procedure; construction verification; field notes; application package; inspection by solid waste control agency.

(Effective January 6, 1982; revised October, 7, 1993)

Rule313. 

            (1)  A verification by a registered professional engineer that the construction of a type III landfill unit was in accordance with the approved engineering plans shall accompany all license applications for newly constructed units.  Construction records that are specified in R 299.4921 shall accompany the verification.

            (2)  An operating license application for a new unit that is upgraded to meet the requirements of these rules shall include as-built plans of the unit that are in compliance with the provisions of R 299.4910.

            (3)  The application package shall be submitted to the solid waste control agency.

            (4)  The solid waste control agency shall make at least 1 inspection of the landfill after receiving a license application and shall, before license issuance, evaluate the status of compliance with the act and these rules.

  Previous|Home|Chapter Contents|Next  

These administrative rules are provided as a free service of the State Bar of Michigan Environmental Law Section.  The administrative rules, which were re-formatted for consistency, are not intended to replace official versions and are subject to revision and/or repeal.  The Environmental Law Section presents this information, without warranties, express or implied, regarding the accuracy of the information, timeliness, or completeness. If you believe the information is inaccurate, out-of-date, or incomplete or if you have problems accessing or reading the information, please send your concerns to the Section.