UNITED STATES DISTRICT COURT
FOR THE WESTERN DISTRICT OF
MICHIGAN
SOUTHERN DIVISION
|
KALAMAZOO RIVER STUDY GROUP, |
|
|
Plaintiff, |
File No. 1:95‑CV‑838 |
|
v. EATON CORPORATION, |
HON.
ROBERT HOLMES BELL |
|
Defendant. |
|
OPINION
This contribution action
under the Comprehensive Environmental Response, Compensation and Liability Act
of 1980 ("CERCLA"), 42 U.S.C. § 9601, et seq., came before the Court for a bench trial on the issue of
liability as to Defendant Eaton Corporation for discharges of PCBs to the
Kalamazoo River ("the River') from its three facilities in Battle Creek,
Kalamazoo, and Marshall, Michigan.
This Court previously
granted summary judgment in favor of Eaton with regard to its Kalamazoo and
Marshall facilities, and ruled in favor of Eaton with regard to its Battle
Creek facility after a bench trial. The basis for those rulings was that the
evidence was not sufficient to show that any of the three Eaton facilities had
released sufficient quantities of PCBs to satisfy the "threshold of significance"
standard.1 The Sixth Circuit reversed this
_________________
16/30/98 Opinion and Order
(Docket # 756 & 757), and 12/7/98 Opinion and Order and Partial Judgment
(Docket # 849 & 850).
Court's rulings with respect
to all three facilities on the basis that this Court applied an incorrect
liability standard to the CERCLA contribution action. Kalamazoo River Study Group v. Menasha Corp. ("KRSG v.
Menasha"), 228 F.3d 648, 650
(6th Cir. 2000).2 The Sixth Circuit instructed that a § 117(f)
contribution plaintiff, like a § 107
plaintiff, is not required to show any direct causal link between the waste
each defendant sent to the site and the environmental harm. Id. at 655‑56. The Court advised
that consideration of causation and other equitable contribution factors is
proper only in allocating response costs, not in determining liability. Id. at 656. Thus, for purposes of this
liability action, the relevant inquiry is whether Eaton discharged any PCBs to the site, regardless of the
quantity. Id. at 658. "[O]ne
discharge [of PCBs] is sufficient to support liability; there is no requirement
that the generator typically discharge waste to the site." Id. at 660 n. 7.
A bench trial on the issue
of liability was held on February 17‑19, 2001. This Court has considered
the testimony of the witnesses, the evidence introduced at this and the
previous trials, the deposition testimony that was admitted into evidence, the
parties' stipulations, and the parties' proposed findings of fact and
conclusions of law. In light of the evidence and the Sixth Circuit's
articulation of the relevant standard, the Court finds that Eaton is liable
under § 117(f) with respect to the Battle Creek and Kalamazoo facilities, but
_________________
2On 1/17/01, pursuant to a stipulation between KRSG
and Menasha, this Court entered an order dismissing without prejudice KRSG's
claims against Menasha, and Menasha's claims against KRSG. (Docket # 969).
Accordingly, the only Defendant left in the liability action was Defendant
Eaton.
2
not the Marshall facility.
This opinion contains the Court's findings of fact and conclusions of law, in
accordance with Fed. R. Civ. P. 52(a).3
Plaintiff KRSG is an
unincorporated association of four paper companies: Millennium Holdings, Inc.
(formerly HM Holdings, Inc./Allied Paper, Inc.) ("Allied"), Georgia‑Pacific
Corporation ("Georgia‑Pacific"), Plainwell, Inc. (formerly
Simpson‑Plainwell Paper Company) ("Simpson"), and Fort James
Operating Company, Inc. (formerly James River Paper Company) ("James
River").
Defendant Eaton Corporation
is an Ohio corporation. At all relevant times, Eaton owned three automotive
manufacturing facilities near the Kalamazoo River, in Battle Creek, Kalamazoo,
and Marshall, Michigan.
In 1990 the Michigan
Department of Natural Resources (now the Michigan Department of Environmental
Quality) ("MDNR" or "MDEQ") determined that a three‑mile
portion of Portage Creek and a thirty‑five mile portion of the Kalamazoo
River from its confluence with Portage Creek downstream to the Allegan City Dam
(the "Site") were heavily concentrated with PCBs. The Site was placed
on the National Priorities List ("NPL") by the United States
Environmental Protection Agency ("EPA") pursuant to Section 105 of
CERCLA, 42 U.S.C. § 9605. The MDNR identified three paper companies, Allied,
_____________________
3Citations to the trial
transcript from the 1/17‑19/01, bench trial will be referred to as Tr. at
__. Citations to testimony from previous bench trials will include the date of
the bench trial.
3
Georgia‑Pacific and
Simpson as potentially responsible parties ("PRPs") for the PCB
contamination. These paper companies entered into an Administrative Order by
Consent ("AOC") which required them to perform a Remedial
Investigation and Feasibility Study ("RI/FS") at the Site.4
The MDEQ has required the PRPs, as part of the RI/FS, to extend their
investigation upstream and downstream of the NPL site to include a ninety‑five
mile stretch of the Kalamazoo River from upstream of the Eaton Battle Creek
facility to Lake Michigan.
For a more comprehensive
factual background on the parties, the history of this NPL Site, and the nature
of PCBs, refer to this Court's previous opinions5 and the Sixth
Circuit's opinion in KRSG v. Menasha, supra.
The Sixth Circuit held that
on remand, the district court should re‑evaluate the liability of Eaton‑Battle
Creek under the proper standard. KRSG
v. Menasha, 228 F.3d at 661. The
Sixth Circuit's reversal of this Court's finding of no liability with respect
to the Eaton‑Battle Creek facility was predicated upon the legal standard
applied by the Court, and not on this Court's factual findings. For purposes of
this second liability trial, however, the parties agreed to allow limited
additional evidence with respect to the Battle Creek facility.
_________________
4Although not a party to the
AOC, James River joined the KRSG and has agreed to participate in the
conducting and funding of the RI/FS.
512/7/98 opinion (Docket # 849); 6/3/00 opinion
(Docket # 942).
4
In light of the new evidence
and legal standard, the Court will amend and restate its findings of fact and
conclusions of law with respect to the Battle Creek facility.
Prior to its demolition in
1984, the Eaton Battle Creek facility was located at 463 North 20th Street,
Battle Creek, Michigan. The plant was approximately one‑half mile from
the Kalamazoo River, upstream of the NPL Site, but within the area to be
studied under the AOC.6
The Battle Creek facility
was in operation from the early 1940s until 1983.7 At the Battle
Creek facility Eaton manufactured parts for the automotive industry, including
internal combustion engine valves and gears.8 During the 1950s Eaton
also ran an Aircraft Division at the Battle Creek facility.9
Manufacturing processes at the Battle Creek facility included heat treating,
forging, welding and machining.10 These processes involved the use
of quench oils, cutting or grinding oils, and hydraulic oils.11 Some
of the heat treating involved temperatures as high as 2500 degrees Fahrenheit.12
____________________
6Uncontroverted Facts, ¶19,
Final Pretrial Order (Docket # 826), Attachment C.
7Uncontroverted Facts at ¶
26; Steven F. Fesko dep. at 40; Kenneth Manchen dep. at 95.
8Uncontroverted Facts ¶ 19.
9Stuart Lightfoot dep. at 13.
10Carleton Swanson dep. at 10.
11Uncontroverted Facts at ¶
21; Lightfoot dep. at 11‑13; Bill
Romick dep. at 9.
12Clifford Galen dep. at 22,
30, 90‑92.
5
There were no floor drains
at the plant. Because the wood floors would swell and buckle if wet, Eaton took
great care to keep water off the floor. Process oils were collected in drip
pans under the machines and under the conveyor belts. Still, residual quench
and cutting oils on parts and waste metals dripped onto the floors, and the
floors became greasy.13 While the machinery was in use it was common
for the cutting, quenching, and water soluble oil to splash or splatter onto
the floor, and for there to be oil standing on the floor at the base of the
machines.14 Oil pipes leading to the machines sometimes leaked, and it
was recalled that on one occasion a high‑pressure hydraulic line burst. 15
Hydraulic operations are
nominally closed operations. The hydraulic systems had filters that kept the
oil clean, so those oils were not thrown away.16 Nevertheless, in
the normal life of a machine that used hydraulics, the hydraulic lines would
need maintenance or would leak from time to time.17
When grinding fines and oils were vacuumed from the machinery reservoirs workers occasionally splashed oil from the hose onto the wood block floor. On one occasion
_________________
13Galen dep. at 22.
14Roosevelt Jones dep. at 107‑08;
James Seaver dep. at 54‑56; Lightfoot dep. at 24-25.
15Jones dep. at 108.
16John Eustis dep. at 55‑56.
17 Galen dep. at 85.
6
multiple gallons of water‑soluble
oils were spilled onto the floor causing the blocks to swell and requiring
replacement of the wood blocks.18
Oils that spilled onto the
floor were either absorbed into the wood block floors or absorbed with a dry
absorbent such as "Floor Dry" or "Speedy‑Dry," swept
up and discarded with the non‑liquid wastes rather than with the
wastewater. The floors in the large aisles and open areas were also cleaned
periodically with a scarifying machine that scraped up the oil residue on the
floors.19 Spills of process oils were common enough that the Battle
Creek facility purchased 2,000 to 4,000 pounds of dry absorbent each month to
keep any spillage from leaking out from around the machines all over the floor.20
The oils that collected in
the pans beneath the manufacturing machines were pumped out and taken to the
mud room where waste metals and sludges were separated. The waste oil was
collected in a tank and the effluent was discharged to the sanitary sewer.21
Clifford Galen, plant manager from 1968‑1973, testified that some of the
drip pans were piped directly to either the sanitary sewer or the storm sewer.22
_____________________
18Chuck Heindrichs dep. at 16‑19.
19Heindrichs dep. at 57‑59.
20Romick dep. at 12‑13.
21Galen dep. at 69‑70.
22Galen dep. at 20, 90‑93.
7
Scrap metal was stored in
open bins outside in the back of the plant, and resulted in some oil run‑off.23
During World War II, and perhaps later, employees dumped solvents, which had
been used for cleaning oil off the valves, directly onto the ground in the
plant back yard.24 Storm drains outside the plant could have carried
some of these oils to the Kalamazoo River.25
Prior to the late 1960s
Eaton had no wastewater treatment system other than a settling weir to settle
out the grinding mud from the water soluble oils.26 The Eaton
facility discharged its wastewater to the City of Springfield Sanitary Sewer
System and the City of Springfield Storm Sewer System.27 Prior to
the mid‑1960s, both the storm sewer and the sanitary sewer discharged to
a ditch which led to the Kalamazoo River.28 It was not until the mid‑1960s
that the Springfield Sanitary Sewer System was connected to the Battle Creek
Sanitary Sewer System.29
____________________
23Swanson dep. at 57‑58;
Galen dep. at 122‑24.
24John Bloemer dep. at 16‑18;
Seaver dep. at 190‑93; Lightfoot dep. at 133‑34.
25Galen dep. at 48.
26Exh. 2019, Environmental
Pollution Survey; Swanson, dep. at 19; Lightfoot dep. at 50; Galen dep. at 16.
27Exh. 2019.
28Swanson dep. at 22‑23.
29Uncontroverted Facts at ¶
22.
8
The effluent that was being
discharged into the storm sewer ran through a concrete pipe under Eaton's
property, and then entered an open ditch that led from Eaton's property to the
Kalamazoo River.30 In 1967 the Michigan Water Resources Commission
("MWRC") conducted a wastewater survey of the Eaton Battle Creek
Plant and determined that the plant was discharging 2220 pounds of oil a day to
the Kalamazoo River via the storm sewers and the ditch.31 Although
the wastewater problem was primarily concerned with the discharge of soluble
oil in solution into the storm sewer and on into the Kalamazoo River, straight
oils were also released to the River.32
When he became plant
engineer in the late 1960s, Clifford Galen observed oily sheens in the effluent
and dark oily stains in the ditch that carried the wastewater to the Kalamazoo
River.33 Galen focused his attention on the problem of oils in
Eaton's effluent, and under his direction the process wastes were diverted from
the storm sewer lines to the sanitary sewer lines.34 Modifications
to the oil disposal room eliminated 1500 to 2000 gallons of oil per day from
the River.35 Used lubricants and cutting oils were collected in
_______________________
30Galen dep. at 16.
31Exh. 2018, 4/10/70 letter
from Eaton to MDNR, referencing 1967 survey.
32Exh. 2011, 1/12/68 letter from Eaton to MDNR; Exh.
2013, 5/10/68 Internal Eaton Memo; Exh. 2014 8/22/68 letter from MWRC to Eaton;
Exh. 2015, 12/23/68 letter from MWRC to Eaton; Galen dep. at 50.
33Galen dep. at 49‑55.
34Galen dep. at 49.
35Exh. 2018, 4/10/70 letter
from Eaton to MDNR.
9
storage tanks which were
removed by a licensed industrial waste hauler for off‑site disposal.36
By December 1969 the amount of oil discharged in the Eaton plant effluent was
reduced to 177 pounds a day.37 In 1973 Eaton constructed an oil
skimming pond to skim oil from its wastewater prior to discharge to the
Kalamazoo River.38
In a 1979 survey, Snell
Environmental Group found that free oils and soluble oils were allowed to enter
the sewer system untreated. The retention pond had a considerable free oil
laver and the definite presence of soluble oils, and the effluent had extremely
high oil levels. The survey team also found oil spill problems in the vicinity
of the drum storage area, which would allow oils to drain into the yard drains.39
Based upon the evidence presented there is no question that over the years Eaton discharged significant quantities of oil to the Kalamazoo River. The discharge of oils to the River, however, does not answer the key question of whether those oils contained PCBs.
Eaton did not retain
documents dating back to the 1940s and 1950s with respect to what oils were
purchased at the Battle Creek facility.40 None of the former
employees at
________________________
36Exh. 2022, 6/11/70 internal
Eaton memorandum re Environmental Pollution Survey.
37Exh. 2018.
38Exh. 2029, 7/17/73 MWRC
Facilities Inspection Report.
39Exh. 2081, Snell
Environmental Group, Phase I Investigations Report: Manchen dep. at 79‑86.
40Fesko dep. at 41‑42.
10
Eaton's Battle Creek
facility, including its stockroom supervisor from 1965 to 1983, recalled any
purchases of Monsanto oils.41 The only oils Eaton employees recalled
being used in the plant were supplied by Shell, Arco, Texaco, Mobil, Amoco and
Standard.42 There is no evidence to suggest that oils from any of
these suppliers contained PCBs at any time.
However, based upon certain
documentary evidence from Monsanto Corporation, the parties have stipulated
that the Battle Creek facility purchased 1940 pounds of Pydraul A 200 from
Monsanto in 1970 and an additional 645 pounds of Pydraul A 200 from Monsanto in
1971. This amounts to approximately 5 drums of Pydraul.43 Pydraul,
is a hydraulic oil containing 100% PCBs.44
PCBs were detected in
Eaton's effluent on two occasions. In February 1972, the MWRC conducted a study
of industrial effluents into various rivers of the state. The sample taken from
the joint outfall from Eaton's Battle Creek facility and Clark Equipment
Company showed 1.4 ppb of PCB Aroclor 1254.45 In September 1972 the
MWRC conducted a wastewater survey at Eaton's Battle Creek facility and found
.24 ppb and .12
_________________-
41See, e.g., Romick dep. at 6‑7, 17‑19; Jones dep. at 187; Ted Wolf
dep. at 46.
42Exh. 2067/6007, 1979
Pollution Incident Prevention Plan; Jones dep. at 59, 163‑64; Romick dep.
at 17, 28, 37‑41.
43Wharton testimony, Tr. at
395 (550 pounds of Pydraul per 55‑gallon drum).
44Stipulation entered 1/9/01,
Docket # 964; Tr. at 4.
45Exh. 2027, Industrial
Effluents at 2; Uncontroverted Facts at ¶ 23.
11
ppb of PCBs in the storm
sewer as it left Eaton's property.46 The MDNR concluded that the
presence of PCBs in the wastewater indicated that Eaton's process wastes were
obtaining entrance to the storm drain.47
Because the storm sewer
lines that were tested did not originate at Eaton and served areas outside of
the plant, the 1972 PCB detections in the effluent cannot be definitively
attributed to Eaton. In addition, the September 1972 test results must be
viewed with some skepticism because the low levels reported were at the limit
of delectability.48
Notwithstanding the
shortcomings of the evidence, the evidence taken as a whole suggests that if
there were PCBs in the effluent, Eaton is the most likely source of those PCBs.
The MDNR survey reveals that Eaton contributed more than 97% of the flow to the
storm sewer, while upstream sources contributed only 3% of the flow.49
Tom Matson, Public Works Director for the City of Springfield, produced maps
indicating that nearly all of the flow through the Eaton ditch came from Eaton.
The only other contributors were the Clark buildings on the east side of 24th
Street and storm water runoff from residential areas
____________________
46Exh. 2028, MWRC 9/25‑27/72
Wastewater Survey; Uncontroverted Facts at ¶ 23.
47Exh. 2028, Wastewater Survey
at 7.
48Plaintiff's expert, Dr. Crumrine, admitted that lie
had testified in another case that testing at a detection limit of less than 1
ppb, even in 1983, was below the concentration level where wastewater
characterization could be reliably determined using state of the art monitoring
procedures. Crumrine testimony Tr. 8/12/98 at 144‑47.
49Exh. 2028.
12
south of the Eaton facility.50
While Clark manufactured hydraulic forklift trucks which could have used PCB‑containing
hydraulic fluid, Matson testified that Clark's principal manufacturing
operations were conducted in buildings on the west side of 24th Street, and
that wastewater from these buildings
was discharged into sewers that led to a ditch west of the Eaton ditch, or to a
storm sewer west past Helmer Road. They did not empty into the Eaton ditch. The
four Clark buildings on the east side of 24th Street that shared the Eaton
sewer line were used for administration, engineering, research and development,
and trucking.51 In light of the uses to which the Clark buildings on
the Eaton line were put, it is reasonable to assume that the PCBs found in the
storm sewer are more probably associated with Eaton than with Clark. The only
other contributor to the Eaton storm sewer was storm water runoff from
residential areas within a several block area south of Eaton.52
Again, although it is not definitively established, this Court can reasonably
conclude that the PCBs were more likely to have originated in the Eaton
industrial facility than from the road surface waters from the residential
area.
In 1980 the MDNR monitored Eaton's wastewater discharge for a twenty‑four hour period. The results showed no traces of PCB. The detection limit used was 0.1 ppb.53 As
__________________
50Tom Matson testimony, Tr. at
39‑49; Exh. 2085NNN.
51Matson testimony, Tr. at 39‑49,
57‑58; Exh. 2085JJJ (Eaton line shown in yellow, Clark line shown in
red).
52Matson testimony, Tr. at 44‑45;
Exh. 2085NNN.
53Exh. 6011, 1/26/81 letter from
Eaton to MDNR Water Quality Division.
13
a result of this test, the
MDNR stopped testing Eaton's effluent for PCBs as a requirement for the NPDES
permit. The MDNR determined that while occasional PCBs may be in the oils used
in the plant, they only appeared at trace contaminant levels.54
When the Eaton Battle Creek facility was demolished in 1983‑1984,
the MDNR requested Eaton to test the wood block floors for PCBs. Eaton was not
averse to complying with the request as its employees had no reason to believe
that there was any contamination.55 Eaton hired Howard Laboratories
to do the testing. Howard tested fifty-five of the approximately 2.8 million
wood blocks on the floor: twenty‑seven samples from under capacitors in
Building C, eleven samples for background in Building C, six samples for
background in Building A, seven samples from the heat treat area in Building B,
and four additional blocks. All fifty‑five samples tested showed the
presence of PCBs in the range of 3.1 mg/kg(ppm) to 155 mg/kg(ppm). The dominant
Aroclors were 1248 and 1254. The wood blocks which contained high oil content
also contained higher PCB content. Of the fifty‑one samples tested for
specific Aroclors, Aroclor 1248 was found in forty‑six samples, Aroclor
1254 was found in forty‑one samples, Aroclor 1242 was found in four
samples and Aroclor 1260 was found in three samples.56
_____________________
54Exh. 6012, 4/3/81 internal
MDNR Water Quality Division memo from Newell.
55Manchen dep. at 56‑67.
56Exh. 2067, Howard Laboratories Inc. Report of PCB
Analyses re Eaton‑Battle Creek, 10/5/83, and Additional Analyses of Floor
Blocks, 10/12/83; Howard dep. at 56.
14
Although Aroclors 1242, 1248
and 1254 were all used in hydraulic oils produced by the Monsanto Corporation,
Aroclor 1248 is the Aroclor most commonly associated with hydraulics.57
According to Dr. Crumrine, Aroclor 1248 was not found in anything other than
hydraulic systems.58 Aroclors 1254 and 1260 are the Aroclors that
are expected to be found in conjunction with capacitors and transformers.59
According to the testimony of Plaintiff’s experts, Aroclor 1254 is the only
Aroclor associated with cutting oils and quench oils sold commercially by
Monsanto.60
Based upon the test results,
Eaton attempted to determine the source of the PCBs. Kenneth Manchen, an
environmental engineer at Eaton, testified that the PCBs were randomly
scattered throughout the facility, and that he was unable to detect a pattern
in their disbursement.61 Stuart Lightfoot, the Director of
Facilities and Plant Engineering, testified that although there were
correlations between some of the higher concentrations of PCBs and the location
of some of the capacitors, he was generally unable to find a pattern that
established a relationship between the locations of electrical equipment and
the PCB
_________________
57Exh. 1372, Aroclors, The Physical Properties and
Suggested Applications, at 15‑17; Exh. 2023, Monsanto PCB Products.
58Crumrine testimony, Tr. 8/12/98, at 98.
59Exh. 2023; Exh. 1372;
Crumrine testimony, Tr. 8/12/98 at 100‑101; Wharton testimony, Tr. at
399.
60Crumrine testimony, Tr.
8/12/98 at 58‑59; McLaughlin testimony, Tr. at 254.
61Manchen dep. at 61‑66.
15
contamination in the wood
block floors.62 Manchen testified that because he did not observe any
definable pattern to the PCBs in the wood flooring, he concluded that in all
probability the PCBs must have come from hydraulic fluids used during the war
years.63
In 1981, VERSAR, an outside
environmental contractor to USEPA, inspected the Battle Creek plant to document
Eaton's compliance with PCB marking and disposal regulations. VERSAR found
several slight leaks from transformers, but no leaks in the in-service
capacitors. VERSAR sampled the cutting, quench and hydraulic oils from various
tanks and machines in the plant and found no detectable levels of PCBs in those
oils.64 VERSAR did detect Aroclor 1242 at a concentration level of 7
ppm in the grinding swarf. Grinding swarf is the sludge created by the process
of grinding metal parts. It usually consists of small particles of the metal
part being ground, the grinding wheel or tool, and the cooling fluid used in
grinding. Because VERSAR did not find PCBs in the process oils, Eaton
personnel, after investigating, concluded that the PCBs in the grinding swarf
likely were attributable to floor scrapings from the floor scarifier being
mixed with the grinding swarf.65
______________________
62Lightfoot dep. at 154.
63Manchen dep. at 73.
64Exh. 2059, Versar Inc. 5/14/81 report on inspection
of Eaton Corporation to determine compliance with PCB disposal and marking
regulations, performed for U.S. EPA.
65Heindrichs dep. at 277‑79.
16
In August 1984 Eaton sent
four soil samples to the Anspec Company, Inc., for PCB analysis. No PCBs were
found in the samples from the north clay beneath sludge, the south clay beneath
sludge, or the north sludge. PCB Aroclor 1254, at 8 ppm, was found in the south
sludge.66
In November of 2000,
Plaintiff’s expert, Michael
McLaughlin, took three samples of sediments from the drainage ditch leading
from the Battle Creek facility. The three samples, B‑1, B‑2, and B‑3,
were within 100 feet of each other. Sample B‑1, which was taken from a
ditch between the railroad tracks and Lafayette Avenue. contained Aroclor 1254
at 12,000 ppb. Sample B‑2, which was taken 15 to 20 feet north of B‑1,
contained Aroclor 1254 at 4,700 ppb, and Aroclor 1260 at 2,400 ppb. Sample B‑3,
which was taken on the north side of Lafayette Avenue, contained Aroclor 1254
at 14,000 ppb and Aroclor 1260 at 4,800 ppb.67 Although Mr.
McLaughlin sought to take samples near the junction of the ditch and the River,
he was unable to locate the ditch along the riverbank.68 The samples
were all taken from a public right of way, and were subject to runoff from the
nearby railroad tracks, Lafayette Avenue, and surface streets in the
residential neighborhood south of the Eaton
__________________
66Exh. 2072, Anspec Technical
Services, Inc., 9/6/84 letter and data summary sheet.
67McLaughlin testimony, Tr. at
293‑96, 307‑16; Exh. 2085JJ, map showing sample locations.
68McLaughlin testimony, Tr.
1/18/01 at 296‑97, 316‑17.
17
facility. Mr. McLaughlin
could not state within any degree of certainty when the PCBs were deposited in
the culvert.69
If the Battle Creek facility
were a source of PCBs, the ditch sampled by Mr. McLaughlin would be an area
where one would expect to find PCBs in the sediments.70 However, Mr.
McLaughlin did not sample any portion of the ditch between sample B‑3 and
the Kalamazoo River, which was 1500 to 1600 feet away. Eaton contends that even
assuming the PCBs in samples B‑1, B‑2 and B‑3 originated from
Eaton, Plaintiff has failed to provide evidence that any such PCBs were
actually transported to the Kalamazoo River clue to the significant distance
(one‑third mile) between sample B‑3 and the River. According to
Eaton this failure is compounded by the lack of evidence of PCBs in the
Kalamazoo River in the vicinity of Eaton's Battle Creek facility.
The experts are in agreement that PCBs in the water tend to settle out with the sediment in depositional areas. There are numerous depositional zones in the fifteen miles between Eaton's Battle Creek facility and Morrow Lake. If PCBs had been released from Eaton they would have shown up in these depositional zones. KRSG has not sampled either sediments or settleable solids immediately adjacent to the discharge point from the Eaton sewer to the Kalamazoo River. In fact, KRSG has not taken any sediment samples in the entire fifteen mile stretch of the River downstream of Eaton's Battle Creek plant. The
_________________
69McLaughlin testimony, Tr. at
at 312‑15.
70Connolly testimony, Tr. at
467‑68.
18
closest sediment sample was
taken in Morrow Lake, approximately fifteen miles downstream of the Battle
Creek facility.71 Instead, for evidence of PCBs in the Kalamazoo
River from Battle Creek to the Morrow Dam, Plaintiff relies on a 1971 MDNR
study, the 1976 Wuycheck study, a 1988 MDNR study, and a 1999 MDEQ study.
In a July 1971 study of the
Kalamazoo River, one water sample downstream of the Battle Creek facility, near
Augusta, Michigan, indicated a total PCB concentration of 0.1 ppb. Because
Plaintiff has not attempted to rule out other industries upstream as potential
sources of the PCBs there is insufficient evidence to attribute this finding to
Eaton's Battle Creek plant. According to Plaintiff’s expert. Dr. Mark Brown, of
Blasland Bouck and Lee ("BBL"), approximately 25% of the Kalamazoo
River watershed (by water volume) is upstream of Battle Creek.72
Moreover, the sample could have reflected effluent from the Battle Creek
Wastewater Treatment Plant which was located approximately one mile downstream
from Eaton's Battle Creek plant.
For purposes of this Court's
determination of Eaton's contribution to PCBs in the River, the Wuycheck data
is perhaps the most relevant because it was undertaken in the mid-1970s, close
in time to when PCBs were being used in industry. If PCBs had been released by
Eaton as alleged by Plaintiff, they should have been detected in the Wuycheck
tests. In 1976, John Wuycheck, an employee in the Biology Section of the MDNR,
conducted an
________________
71Brown testimony, Tr. at 178.
72Brown testimonv, Tr. 8/10/98
at 80‑81.
19
"intensive" survey of both sediment and settleable solids (also known as suspended solids) in the Kalamazoo River. Of the six locations tested between the Battle Creek plant and Morrow Lake, the only positive sediment samples came from 35th Street in Galesburg (K‑12), where he detected Aroclor 1254 at 1190 ppb, and Morrow Pond at Rosemont St. (K‑13), where he detected Aroclor 1254 at 3140 ppb. These sites are approximately thirteen and fifteen miles downstream of Eaton's Battle Creek facility. The sediment sample from the site closest to the Eaton Battle Creek plant, Stringham Road (K‑8), was non‑detect for PCBs.73
The Wuycheck study also detected no PCBs in the suspended solids from the Stringharn Road (K‑8) site. It did detect PCBs at a level of 1140 ppb in suspended solids at Custer Road (K‑9), approximately five and one‑half miles downstream of the Battle Creek facility and at a level of 810 ppb at 38th Street in Galesburg (K‑11), approximately eleven miles downstream of the Battle Creek facility. The detection of PCBs in the water column over five miles downstream of the Eaton Battle Creek facility also tells little to nothing about the Eaton Battle Creek facility. Since almost twenty‑five percent of the watershed for the Kalamazoo River is upstream of Battle Creek, PCBs in the water column could be from unknown point sources, runoff, and air pollution. The Custer Road collection point was also within the plume of the Battle Creek Wastewater Plant. Furthermore. even though the settleable solids test is useful for determining the presence of PCBs in the water column, it
________________
73Exh. 2036/6110, John Wuycheck 4/13/77 Sediment and
Settleable Solids Samples Kalamazoo River, 1976.
20
is not helpful in
determining the source, quantity or concentration of PCBs. In a settleable
solids test the collection bottles are suspended in the water for a period of
time during which particles from the water and organic film accumulates in the
bottle and collects PCBs from the water column. Because the organic materials
in the bottle tend to attract PCBs, the test may indicate an artificially high
reading of PCBs.74
In 1988 the MDNR tested the sediment at eleven locations between Battle Creek and Morrow Lake. Only one of the eleven sediment samples tested positive for PCBs. PCBs at a concentration level of 1000 ppb of Aroclor 1254 were detected at one location downstream of the Battle Creek facility and 0.3 kilometers upstream of the discharge point of the Battle Creek Wastewater Treatment Plant.75 The sediment tests from the remaining ten locations were all non‑detect for PCBs.
Plaintiff KRSG contends that the lack of positive tests for PCBs in the 1988 study is deceptive and should not be relied upon to show the absence of PCBs in the River because the MDNR used a high detection limit of one part per million (1000 ppb). Plaintiff's argument ignores the burden of proof. This Court will not guess what the use of lower detection limits might have shown. Plaintiff bears the burden of proof on the issue of Eaton's contribution to the PCBs in the River. If Plaintiff was dissatisfied with the available studies, Plaintiff could have done its own studies of this portion of the River.
________________
74Brown testimony, Tr.
8/10/98, at 75‑77.
75Exh. 6020. 7/7/88 MDNR
Qualitative Biological Survey of Kalamazoo River.
21
The experts were in
agreement that PCBs are normally found in greatest concentration in
depositional areas closest to the source. Plaintiff would like the Court to
infer that the sediments might have been disturbed or blown out by floods or
the removal of dams on the River. This theory is not supported by the evidence.
Eaton's expert, Dr. Connolly, sampled the sediment in Morrow Lake for a form of
Cesium, an element deposited by the atmospheric testing of nuclear weapons
beginning in 1954. The Cesium analysis revealed that Morrow Lake sediments have
remained virtually undisturbed since before 1954.76 The sediments in
Morrow Lake are accordingly a reliable source of information on PCBs that were
historically released to the River.
The MDEQ's recent sampling of the River water similarly adds little support to Plaintiff’s case. In September and October 1999, the MDEQ collected water column samples from various locations in the Kalamazoo River. Two of the samples are of particular interest in this case. One sample was taken just downstream of the Ceresco Dam, upstream of Eaton's Battle Creek and Marshall facilities. Another sample was taken at the 35th Street Bridge in Galesburg, just upstream of Morrow Lake. These two locations are approximately thirty miles apart. PCBs were detected at levels of approximately 3.5 parts per trillion at both locations. Because there are depositional areas between those two points in the River, this data indicates that there is no evidence of PCBs fluxing from sediments in the region between the Ceresco Reservoir and Morrow Lake. If there were sources of PCBs
_____________________
76Connolly testimony, Tr.
8/14/98, at 37‑39.
22
upstream of Morrow Lake, one
would expect to see the concentrations increase, and to be higher at the
downstream station. The PCB level detected. 3.5 ppt, is a relatively low level
of PCBs. It is typical of levels observed in precipitation in the Great Lakes
area, and typical of PCB levels in rainwater or snow. Studies of rainwater in
the Great Lakes region indicate PCB levels in rainwater ranging from 1 ppt to 7
or 8 ppt. PCB levels of 2‑4 ppt are found in remote lakes in Ontario,
Canada.77
In March 2000, the KRSG initiated a Surface Water Sampling Program in the Kalamazoo River. Sampling locations included one station near Galesburg, downstream of Eaton's Marshall and Battle Creek facilities. Samples were taken every two weeks from March through July of 2000. PCBs were not detected in any of the eleven water column samples. The detection limit used was six parts per trillion. Ten additional water column samples were collected during elevated flow in the River when sediments from the bottom of the River would likely be resuspended and transported downstream in the water column. PCBs were not detected in any of those samples, either. Dr. Connolly testified that if there were PCBs in the sediment he would expect to see them in the water column, particularly during a high flow event where sediments would likely be resuspended off the bottom. According to Dr. Connolly, the Kalamazoo River data indicates no detectable releases of
__________________
77Connolly testimony, Tr. at
449‑53.
23
PCBs from Eaton's Marshall
or Battle Creek facilities, or any other facilities between Marshall and Morrow
Lake.78
The KRSG's fish data taken
from 1993 to 1997 in the vicinity of Battle Creek showed PCB concentrations of
.04 ppm to. 14 ppm, with a single value outside of that range, which was at .24
ppm. These numbers are consistent with the earlier sampling done by the MDNR in
1987 in the Ceresco Reservoir, upstream of Eaton's Battle Creek facility, where
they found PCB levels in fish at levels ranging from .02 to .12 ppm. Both the
levels found by the MDNR as well as the levels found in KRSG's more recent
sampling are similar to levels found at background sites. These background
sites are from around the country where there are no known PCB sources, and the
only believed source of PCBs is atmospheric deposition. Downstream, within the
Superfund site, the PCB levels in fish are considerably higher than they are in
the vicinity of Battle Creek.79
The information gathered from the River sediments, water, and fish is of primary relevance to the issue of allocation because it bears on such issues as quantity and frequency of PCB releases from the facility. It is of less importance in determining the discrete question presented here, i.e., whether any PCBs were released from the Eaton property to the River. However, it does have some relevance in determining which oils used at Eaton's Battle Creek facility contained PCBs.
_______________
78Connolly testimony, Tr. at
454‑55.
79Connolly testimony, Tr. at
455‑57.
24
Plaintiff suggests that because Aroclor 1254 has been associated with cutting oils and quench oils in the literature and in some heavy industries, because Aroclor 1254 was found in all areas of the plant where machining processes occurred, because Aroclor 1254 was found in the ditch leading to the Kalamazoo River, and because the highest PCB levels were associated with the wood blocks with the highest oil content, the only reasonable conclusion is that the process oils used historically in cutting and quenching operations at the Battle Creek facility contained PCB Aroclor 1254.
The Court does not find that
such a conclusion is warranted. The evidence indicates that PCBs were not a
common additive in cutting and quenching oils. Although Monsanto marketed PCB‑containing
cutting oils, PCB‑containing cutting oils were not commercially
successful.80 There is no reason to add PCBs to cutting oils, there
is no chemically feasible way to add them to soluble oils, and there were many
better and cheaper alternatives to adding them to quench oil.81 Dr.
Howard, an environmental consultant who owned and operated chemical
laboratories from 1971 until 1989, tested approximately 100,000 samples for
PCBs. In that testing he recalled only one group of cutting oil samples, no
soluble oil samples, and only two groups of quench oil samples that tested
positive for PCBs.82 Plaintiff
________________
80Wharton testimony, Tr. at
400.
81Wharton testimony, Tr. at
383‑85.
82David Howard dep. at 6, 17‑21,
23, 32.
25
has not offered evidence to
persuade this Court that Eaton's Battle Creek facility would have chosen to use
PCB containing cutting and quenching oils.
Due to the fact that not
many wood blocks from the floor of the Eaton Battle Creek facility were tested,
and the majority of the blocks tested were from the vicinity of transformers or
capacitors that were thought to have contained PCBs, the testing of the wood
block floors is not representative of the floor as a whole. The wood block
floor testing is insufficient to show the widespread dispersal of PCBs that
would be indicative of the use of PCBs in quench and cutting oils at the
facility.
The evidence in the River also does not support Plaintiff's argument that Eaton used PCBs in its quench and cutting oils. In fact, the evidence from the Kalamazoo River supports the opposite conclusion that the discharge of PCBs was small and related to oils used in closed or nominally closed systems. The evidence shows that Eaton was discharging a ton of oil per day in the 1960s. The majority of those oils would come from its open systems, i.e., its cutting and quench oils. If those cutting and quenching oils contained PCBs, they would be expected to show up in the River sediments near or immediately downstream of the plant. There is no evidence of that. The Court is struck by the lack of evidence regarding PCBs at or near the outfall of the drain from Eaton to the River. As the party with the burden of proof in this matter, the Court would have expected KRSG to have presented some evidence of River contamination close to Eaton's Battle Creek plant.
26
The Court is also struck by
the complete lack of evidence of Aroclor 1248 in the Eaton ditch or in the
River between Eaton's Battle Creek facility and Morrow Lake. Since Aroclors
1254 and 1248 were both in the floor of Eaton's plant, one would expect that if
Aroclor 1254 from the Eaton facility reached the River, Aroclor 1248 would have
reached the River as well. Yet Plaintiff has come forward with no evidence of
Aroclor 1248 in the ditch or in the River downstream of Eaton and upstream of
Plaintiff’'s members.
Upon reconsideration of the evidence produced at the first trial in light of the new evidence Plaintiff has produced at this trial, this Court abides by its initial determination that the evidence does not support a finding that the PCBs at the Battle Creek facility were related to cutting and quenching oils. Plaintiff has not shown that PCBs were necessary to Eaton's cutting and quenching processes. Plaintiff has not shown that Eaton purchased PCB‑containing quench or cutting oils. Plaintiff has not shown PCBs in the River that would indicate the use of PCBs in open systems. Because Plaintiff is the party with the burden of proof, and because the PCBs at Eaton's Battle Creek facility can all be explained by reference to leaks from hydraulic and di‑electric equipment, the Court finds that the PCB contamination at Eaton's Battle Creek facility is not attributable to the use of PCBs in quench and cutting oils. Rather, this Court finds that the PCBs at the plant are attributable to leaking transformers, capacitors and hydraulic systems.
Because di‑electric
and hydraulic systems are closed or nominally closed systems, the Court finds
that the quantity of PCBs released in the waste oils was minimal. Still. it is
fair
27
to conclude that it is more
likely than not that some very small quantity of PCBs probably found their way
to the Kalamazoo River.
In the first trial Plaintiff offered no evidence that the PCBs had found their way to the ditch or to the River. Now Plaintiff has, for the first time, come forward with evidence of PCBs in the Eaton ditch. Eaton contends that Mr. McLaughlin's testing does not add anything of significance to KRSG's case against the Battle Creek plant because 1) the sediments sampled in a culvert near the former location of the plant were taken from a public right of way to which anyone had access and which was subject to runoff from Lafayette avenue and the railroad tracks; 2) Mr. McLaughlin could not determine when the PCBs were deposited in the culvert; 3) the Aroclors detected are commonly associated with di‑electrics; and 4) the sample nearest the River was still approximately 1/3 of a mile away. Eaton contends that because KRSG has presented no samples from the riverbank where the Eaton ditch discharged to the Kalamazoo River, KRSG has failed to connect the dots and to show that a discharge at one location caused a response action at a second location.
Eaton's attempt to compare
this case to KRSG v Rockwell Int'l Corp.
("Benteler"), 171 F.3d 1065, 1068 (6th Cir. 1999), is not
persuasive. Unlike Benteler, there
was no evidence in this case that the ditch was not an active water course
connecting the facility with the River. To the contrary, the evidence reveals
the discharge of large quantities of effluent from Eaton, through the ditch, to
the Kalamazoo River.
28
Plaintiff has established by
a preponderance of the evidence that some small quantity of PCBs probably went
to the River. Based upon Eaton's purchase of PCB‑containing hydraulic
oil, the presence of PCBs on the plant floor, the detection of PCBs in Eaton's
effluent, and the detection of PCBs in the Eaton ditch, it appears to this Court
that it is more likely than not that some of the PCBs from the Eaton plant
found their way into the sewer system and to the ditch. Even if the bulk of the
spills of PCB‑containing di‑electric or hydraulic oils was absorbed
by the floors or swept up and discarded, some of the oil would probably have
mixed with the process oils and found its way into the effluent from the
facility. Although organics in the slow‑moving ditch would have acted as
a magnet and a trap for PCBs, the Court finds that some, albeit very few, PCBs
would have found their way to the River.
While the new evidence does not change this Court's previous conclusion that there is insufficient evidence of a detectable or measurable discharge of PCBs from Eaton's Battle Creek plant into the Kalamazoo River, under the liability standard articulated by the Sixth Circuit, this Court is constrained to find that Eaton is liable for some PCB releases from its Battle Creek facility to the Kalamazoo River.
III. KALAMAZOO FACILITY
Eaton manufactured truck transmissions at the Eaton Transmission Division on Mosel Avenue in Kalamazoo, Michigan, from the mid‑1950s until January 1984, when the plant was closed. Eaton was the sole occupant of the building. The plant was serviced by City
29
sewer and water. The plant
was located approximately a half mile from the Kalamazoo River.
The plant's processes
included machining (cutting, turning and hobbing), heat-treating and polishing
transmission parts such as gears, shafts, and housings, and assembling those
parts into truck transmissions.83 These operations required the use
of water soluble cutting oils. synthetic cutting compounds, and quench oils.84
There were no die‑casting or forging operations at the plant.85
Parts that went through the
heat treat furnaces went into a quench oil bath, and then were washed. When
David Martin, plant engineer at Eaton's Kalamazoo facility from the mid‑1960s
to the mid‑1980s. first started at Eaton, the sewer lines from the heat
treat department and from some of the manufacturing areas discharged to a catch
basin, from which it was pumped to the Zantman drain. The oils that went into
the drains were primarily the water soluble oils.86
Parts were also washed after machining operations in other areas of the plant. Prior to the late 1960s, the wastewater from those operations, including waste oils, were passed
_________________
83Exh. 2212, 1985 GZA Environmental Site Assessment;
Exh. 6114, 1976 MDNR Industrial Wastewater Survey; Exh. 2232, 1978 MDNR
Discharge Permit Application.
84Exh. 2215, 1967 MWRC Industrial Survey.
85Brown testimony, Tr. at 179.
86Martin dep., vol. 1, at 14, 21‑22, 46, 50, 54‑55:
Martin dep., vol. 2, at 28‑29; Exh. 2233, 1968 MWRC Industrial Wastewater
Survey.
30
through a decanter system,
then discharged to the catch basin, the City sanitary sewers or the City storm
sewers. The catch basin and some of the storm sewers discharged to the Zantman
Drain. Other sewer lines discharged to the municipal sanitary system or the
municipal storm water system. The catch basin removed some oils, but other than
that there was no treatment before the water, mixed with oils, was discharged
to the Zantman Drain, the sanitary sewer, or the storm sewer system. 87
During the manufacturing
process, cutting oils, hydraulic oils and oil‑based coolants commonly
spilled onto the wood‑block floors.88 After a part came off a
machine it would be placed on a spindle or cart. There was a pan under the
carts, but oil was bound to splash and drip onto the floor. Most of the oil
that was lost while a machine part was in transit from one manufacturing area
to another.89 Enough oil dripped on the floor to require the use of
large quantities of Floor Dry or Oil Dry.90 Waste from the scarifier
used to clean the floors was placed into one of several trash compactors, and
fluids from some of the compactors would run into floor drains.91
Until the mid‑1970s, the floor drains at the Kalamazoo facility led to
either the Zantman Drain, the storm sewer, or the sanitary sewer.
__________________
87Martin dep., vol. 1 at 16‑29;
Martin dep., vol. 2 at 137; Exh. 2233, 1968 MWRC Industrial Wastewater Survey.
88Baker dep. at 36‑40;
Duane Clarke dep. at 47.
89Clarke dep. at 19‑21;
David Stephayn dep. at 34‑ 35, 39.
90Clarke dep. at 21‑22;.
Martin dep., vol. 2, at 62.
91Martin dep.. vol. 2, at 62‑64.
31
Because oil was expensive,
it was generally recycled and reused.92 Straight oils would be
recycled or picked up by waste haulers.93 Carl Baker, who started
working at Eaton corporation in the 1950s, testified that quench oil, in
particular, was continually reused, and he did not recall any spills of quench
oils.94 Hydraulic oils
were filtered and reused. Although hydraulic lines would break periodically
with a loss of two or three gallons of oil at a time, most of the time the oil
went right into the cutting oil reservoir.95 Some oil spilled on the
ground outside the building. There was staining outside the heat treat area
where the tankers would fill the tanks.96 On occasion spills
occurred when a chip operator was hauling chips, or when an oil line froze.97
Some of the storm water from off the property went to the catch basin, and was
discharged to the Zantman drain.98 Other storm drains went to the
municipal storm water system.99
_________________
92Clarke dep. at 17‑20.
93 Martin dep., vol. 1, at 50‑51.
94 Baker dep. at 14, 38‑40.
95Clarke dep. at 17‑18,
45‑46.
96CIarke dep. at 51‑52.
97Martin dep., vol 2, at 128‑29.
98Exh. 2233, 1968 MWRC
Industrial Wastewater Survey.
99Martin dep., vol. 1 at 25:
Clarke dep. at 30‑31.
32
Metal shavings and trimmings
were dumped into a collection pit outside of the plant. Oils were drained from
the trimmings pooled on the ground under and around the pile.100
Periodically the shavings were lifted off with a magnet separator, and the oil
was pumped out and hauled away.101
The catch basin did not
prevent all the oil from entering the Zantman Drain.102 In March
1965, the MWRC tested the water in the Zantman Drain and found that it
contained oil in concentrations of 41 and 51.2 ppm. The MWRC advised that Eaton
was responsible for the excessive quantities of oil in the Zantman Drain, and
for the oil pooling in the swampy area north of Mosel Street. The MWRC further
advised that "[t]he amount of oil being lost to the drain would undoubtedly
create oil pollution problems in the Kalamazoo River were this drain to be
cleaned out to the river."103 The MWRC advised Eaton that it
had to improve its waste control methods to correct the contamination of the
Zantman Drain and groundwater.104 Eaton acknowledged that as a
result of the practice of emptying its
__________________
100Exh. 2215, 1967 MWRC
Industrial Survey.
101Clarke dep. at 30.
102Martin dep., vol. 1 at 22.
103Exh. 2213, MWRC March 1965 Report of Survey. See also 11/14/67 letter from MUCC to
MWRC complaining about Eaton's discharge of oils to the Zantman Drain, and
expressing concern that if plans to improve the drain are carried out, the oils
will flow directly into the Kalamazoo River.
104Exh. 6302, 5/14/65 letter from Eaton to County Drain
Commissioner, quoting from MWRC's 3/23/65 survey.
33
metal shavings coated with
cutting oil outside, "a great deal of oil accumulates in our yard which
seeps into and at times of substantial rainfall washes into the drainage
ditch." 105
The 1967 wastewater survey showed that Eaton was
releasing oil at concentrations of 373 ppm, for an estimated release of 1332
pounds of oil per day. The MWRC noted that heavy deposits of oil had
accumulated along the banks of the Zantman Drain and around the periphery of
the waste ponding area. According to the MWRC, the major source of this oil is
from parts washers in the heat treating department. The MWRC was also concerned
that the oil pooled around the scrap metal pile could be washed overland into
the Zantman Drain during times of heavy precipitation.106
Eaton responded to the
MWRC's concerns by making changes in its waste disposal system. A concrete pit
was constructed to catch oil drippings from the scrap metal pile.107
A free oil skimmer was installed at the outlet of the collection basin.108
By the early 1970s most of the floor drains were plugged to prevent the
active disposal or accidental drainage of water and oil into the floor drains. 109
A clarifier was installed in the mid‑ 1970s.110
______________________-
105Exh. 6302, 5/14/65 letter
from Eaton to County Drain Commissioner.
106Exh. 2215, MWRC June 1967
Industrial Survey.
107Exh. 2216, 10/23/67 letter
from Eaton to MDNR; Exh. 2217, 1/29/68 letter from Eaton to MDNR.
108Exh. 2216, 10/23/67 letter
from Eaton to MDNR; Martin dep., vol. 2 at 31.
109Martin dep., vol. 1 at 56‑57;
Martin dep., vol. 2 at 26, 158; Baker dep. at 19.
110Clarke dep. at 29‑30.
34
All process water and
cooling water was discharged to the collection basin or settling lagoon where
sediment was allowed to drop out. In early 1974, Eaton advised the MWRC that it
had recently completed construction of a detention pond for oil removal.
"Both the storm drain and the process water which originally went to the
Zantman Drain are now directed to the detention pond."111 An
oil skimmer was installed on the lagoon to keep the oil from being discharged
to the Zantman Drain.112 Free floating oils were skimmed and
collected in a holding tank. Water from the collection basin was pumped into
the Zantman Drain. The waste from the holding tank was pumped through a
decantering system, with the wastewater going to the sanitary sewer and the oil
being hauled away by commercial carrier.113 Despite the installation
of the oil skimmer on the pond in the early 1970s, the skimmer did not prevent
all oils from reaching the Zantman Drain.114
The Zantman Drain is a county drain under the jurisdiction of the Kalamazoo Drain Commission. Prior to approximately 1973 when it was reconstructed, the Zantman Drain was an open culvert that began west of the Eaton facility, came across to the east side of the Eaton facility, then turned north where it tied into the Richardson Drain. It went through a
____________________
111Exh. 2220, Briefing Memo for
NPDES Application.
112Exh. 2219, MWRC 1973
Industrial Wastewater Survey; Exh. 6113, 1976 MDNR Industrial Wastewater
Survey.
113Exh. 2232, 1978 MDNR
Discharge Permit Application.
114Stephayn dep. at 97‑98.
35
culvert under Mosel Avenue,
through a 24 inch pipe under the Upjohn Building. then into an open ditch
before discharging into the Kalamazoo River.115
There was not much
contribution to the old Zantman Drain from upstream of the Eaton Kalamazoo
facility. There was little evidence of a water course west of Burdick Street.
Most of the land west of the Eaton facility was agricultural, so there was
little industrial development that would have contributed to the Zantman Drain.116
In the 1960s and early 1970s
there was concern that the Zantman Drain was inoperative due to construction
over the drains, improper grading, debris, and plant growth. The obstruction
caused wastewater to pond in a marshy area and to back up on the properties
just north of Mosel Avenue. There was not much flow in the drain north of Mosel
Avenue. There was only a trickle from the 24 inch pipe underneath the Upjohn
Buildings through to the ditch on the north side of the Upjohn property. The
minimal flow through the drain to the Kalamazoo River, however, would have
increased during a heavy rain.117
In 1973 the Zantman Drain was improved and relocated. The entire section of the drain between the Eaton facility and Mosel Avenue was enclosed in a corrugated metal pipe.
__________________
115Robert Snell testimony, Tr. at 71, 83; Exh. 2230,
1966 diagram of Zantman Drain; Exh. 2200A, 1955 Aerial Photograph; Exh. 2201,
6/8/64 letter from Snell to Kalamazoo Township Board; Exh. 2085KKK, aerial
photo and overlay.
116Snell testimony. Tr. at 81‑82.
117Snell testimony, Tr. at 84, 89‑90; Exh. 2201,
6/8/64 letter from Robert E. Snell to the Kalamazoo Township Board: Exh. 6300,
5/4/64 letter from Eaton to County Drain Commissioner; Exh. 2253, 10/21/65
letter from Eaton to County Drain Commissioner.
36
The portion of the new drain
north of Mosel Avenue was an open ditch, east of the former channel. The drain
ran north from Mosel past the Southon Paper Company, then east across the back
part of Southon's property, then north along the railroad tracks to the River.
Over 15,000 cubic yards of dirt were excavated for the open drain north of
Mosel Avenue. That dirt was not hauled away. It was left on the banks or spread
on neighboring property. 118
In a 1965 study, Eaton was
found to be discharging 433,000 gallons of wastewater per day to the Zantman
Drain.119 In a 1968 study, Eaton was found to be discharging 459,000
gallons of wastewater per day to the Zantman Drain.120 Given this
magnitude of flow on a daily basis, Dr. Brown opined that it would be difficult
to contain all the wastewater in the marshy area north of Mosel Avenue without
some of that water flowing thorough the drain towards the Kalamazoo River.121
Heavy rains would also have carried water through the drain to the River.122
There is no dispute that once the Zantman Drain was improved in 1973, effluent discharged by Eaton through the Zantman Drain did reach the Kalamazoo River. There is also no question that some oils were carried from the Eaton facility to the River. The
_______________
118Snell testimony, Tr. at 92‑103; Exh. 2085M,
map of Zantman Drain; Exh. 2200‑D, 1974 Aerial Photograph; Exh. 2200‑E,
1991 Aerial Photograph.
119Exh. 2213, MWRC 1965 Report of Survey.
120Exh. 2233, MWRC 1968 Industrial Wastewater Survev.
121Brown testimony, Tr. at 211‑12.
122Snell testimony, Tr. at 89‑90.
37
NPDES permit itself allowed
a daily maximum release of l0mg/l of oil from the Eaton Kalamazoo facility to
the Kalamazoo River via Zantman Drain.123 In a 1973 letter to Eaton,
the Kalamazoo County Drain Commissioner stated that in his "recent
inspection and observation of the Zantman Drain there seems to be an oil film on the water as it escapes into the
Kalamazoo River."124 In 1974 and 1975, an engineering company
noted that after a physical inspection of the Zantman Drain it found "a
collection of oil on the water surface and adjoining banks where the water
level has fluctuated." 125 Although Eaton has suggested that
the oils might be attributable to other sources, there is nothing in the
historical record to suggest that Eaton ever objected to the Drain
Commissioner's implication that Eaton was responsible for oils reaching the
Kalamazoo River.
The question for this Court
is whether there were PCBs in those oils. There is no evidence of any testing
of the process oils at the Kalamazoo facility that would indicate the presence
of PCBs, and there is no testimony from any Eaton employee that PCBs were used
in any of the process oils at the plant.126 Duane Clarke began
working for Eaton in 1967,
and was the general foreman
of machine repair from 1968 until the plant closed in 1985.
_______________________
123Exh. 2206, MWRC 3/29/74 NPDES Permit.
124Exh. 2226, 12/19/73 letter from Kalamazoo County
Drain Commissioner to Eaton.
125Exh. 2202, 12/16/74 letter from Wilkins &
Wheaton Engineering Co. to Kalamazoo County Drain Commission; Exh. 2203,
12/8/75 letter from Wilkins & Wheaton Engineering Co. to Kalamazoo County
Drain Commission.
126Brown testimony, Tr. at 179.
38
He testified that he did not
know of any PCB‑containing oil used at the Kalamazoo facility. Most of
the hydraulic oil purchased was Mobil. Clarke did not know of any reason why
the oils used would have to have PCBs. The only PCBs Clarke was aware of were
those in transformers or capacitors.127
In the 1973 industrial wastewater survey the MWRC, for the
first time, tested the effluent from Eaton's Kalamazoo facility for PCBs. No
PCBs were detected.128 The industrial wastewater survey of 1976
similarly detected no PCBs in Eaton's effluent.129
In 1984, in connection with
Eaton's sale of the Kalamazoo facility to Liberty Properties, Eaton tested
seventy samples of the wood block floors. PCBs were found in the wood flooring
in levels ranging from non‑detect to 743 ppm. No distinction was made in
the study between the various Aroclors. The floor map indicates where the
samples were taken, and whether they were taken from the aisle, background,
capacitors, or transformers. Of the sixty‑nine samples taken, twenty‑eight
samples were below the detection limit. Only four samples contained PCBS in
excess of 20 ppm, and all four of these samples were from locations near
transformers or capacitors.130
_________________
127Clarke dep. at 4, 10, 13, 46, 57, 63‑65.
128Exh. 6113, 1973 MWRC Industrial Wastewater Survey.
129Exh. 6114, MDNR 1976 Industrial Wastewater Survey.
130Exh. 2209, Eaton Floor PCB
Analyses.
39
Stuart Lightfoot was manager
and then director of Environmental Engineering at Eaton's Battle Creek facility
for nineteen years. Sometime after learning about the PCB contamination of the wood floors at Battle Creek, he
learned that there were also small areas of PCB contamination in the wood block
floors at the Kalamazoo facility. He thought the cause of the PCB contamination
was a leaking transformer and the heat treat oil quench operation. 131
Lightfoot's testimony
regarding the possibility of PCBs in the quench oil is not persuasive.
Lightfoot did not test the quench oils at Kalamazoo. He merely assumed there
might have been PCBs in the quench oil because the Kalamazoo facility heat
treat department did not have automatic fire extinguishers on it.132
In light of the fact that the facility was operational until 1983, long after
PCBs were no longer available in quench oils, the absence of fire extinguishers
in the quench department tends to lead to the opposite conclusion, i.e., that
the temperatures in the heat treat department were not high enough to require
either PCBs in the quench oil or fire extinguishers.
After the Eaton Kalamazoo Plant was sold in 1984, an environmental due diligence investigation was performed by an environmental consultant, GZA, retained by the purchaser. The investigation included thirty‑one soil and water samples. The only PCBs
__________________
131Lightfoot dep. at 5, 172‑73.
132Lightfoot dep. at 175.
40
mentioned in the
environmental report were those detected in the wood block flooring in the
study conducted by Eaton.133
In 2000 the MDEQ conducted Aroclor‑specific testing at the Kalamazoo facility. PCBs were detected in soil, concrete, floor blocks and wipe samples. In contrast to the testing of a limited number of wood blocks from strategic areas at the Battle Creek facility, the testing at the Kalamazoo facility was done in a variety of areas throughout the facility. Very few PCBs were detected in soils and no PCBs were detected in the groundwater.134 The MDEQ's 2000 data shows a predominance of Aroclors 1254 and 1260. Aroclor 1260 was detected primarily in wipe samples. It was not detected in any of the soil samples under or adjacent to the facility. Only one sample from within the building contained Aroclor 1248. Aroclor 1242 was not detected anywhere in the plant or on the adjoining property, except in one isolated sediment sample from the former settling pond.135 Because there was no evidence of Aroclor 1242 in the building, this detection is probably explained by the fact that the settling pond was lined with paper mill sludge.136
__________________
133Exh. 2212, GZA Environmental
Site Assessment.
134Exh. 6305, Eaton's demonstrative exhibit depicting
results of 1984 and 2000 PCB testing; Exh. 2085MM, Plaintiff’s demonstrative
exhibit depicting results of 1984 and 2000 PCB testing; Barrick testimony, Tr.
at 489.
135Barrick testimony, Tr. at 489, 492‑93; Wharton
testimony, Tr. at 391.
136Exh. 6145, 1/10/72 letter from MWRC to Eaton,
approving Eaton's plan to line settling basin with paper mill sludge; Barrick
testimony, Tr. at 492‑93.
41
Dr. Brown testified that the
detection of Aroclor 1248 at a fairly high concentration in a wipe sample (120
ppm) as well as the detection of PCBs in soils beneath the plant, in some cases
as deep as fifteen feet or more below the concrete, indicate that the PCBs are
more likely to have come from cutting oils or hydraulic fluids than from only
capacitors and transformers.137 Mr. McLaughlin testified that when
he considered the distribution of samples and removed one anomalous transformer
result and two anomalous capacitor results, there was no difference between the
electrical samples and the background or aisle samples. According to Mr.
McLaughlin, finding PCBs at depth beneath the heat treat department is an
indication that these PCBs were in the quench oil. He also testified that PCBs
of electrical origin do not typically migrate to such depths. From his
consideration of all the data he concluded that the PCB detections were not
principally related to capacitor and transformer leaks.138
This Court agrees with Dr.
Brown and Mr. McLaughlin's conclusion that in light of the detection of Aroclor
1248, the PCB detections cannot all be ascribed to capacitor and transformer
leaks. While Mr. Barrick testified that there is a possibility that some
electrical equipment could contain Aroclor 1248, the documentary evidence does
not indicate that this application of Aroclor 1248 was recommended or
advertised.139 The Court finds that it is
_________________
137Brown testimony, Tr. at 202.
138McLaughlin testimony, Tr. at 269, 275‑76; Exh.
2085MM.
139Barrick testimony, Tr. at 493; Exh. 2023, Monsanto
PCB Products at 3‑4; Exh. 1372, Aroclors, The Physical Properties and
Suggested Applications, at 9.
42
more likely that the single
detection of Aroclor 1248 indicates the presence of PCBs in hydraulic fluid
that leaked on the floor.
The Court does not agree
with Plaintiff’s assertion that the predominant Aroclors found at the Kalamazoo
facility, Aroclors 1254 and 1260,
are more likely to be attributable to PCBs in cutting or quench oil than to the
oils from the di‑electric equipment. Aroclors 1254 and 1260 are the same
Aroclors one would expect to find in electrical equipment. Dr. Brown conceded
that the evidence of PCBs in the wood block floor at the Kalamazoo plant could
be consistent with periodic leaks from transformers and capacitors. He also
acknowledged that the presence of PCBs at depth can be explained by the use of
detergents which would bring the PCBs down into the soil. 140 Mr.
McLaughlin was unable to explain the absence of any PCBs detected in the chip
storage area, where process oils would have drained off the metal chips into
the soils.141
The testing of the Eaton
Kalamazoo facility in 1984 and again in 2000 revealed that the PCB
concentrations were primarily of a low level, either non‑detect or up to
a few parts per million, in a sporadic pattern throughout the facility. The
highest concentrations of PCBs were found near the electrical equipment areas.142
The lower levels of PCBs were
____________________
140Brown testimony, Tr. at 184,
202; Exh. 2216, 10/23/67 letter from Eaton to MDNR, documenting use of
detergents.
141McLaughlin testimony, Tr. at
331‑34.
142Brown testimony, Tr. at 143;
Wharton testimony, Tr. at 370‑8S; Barrick testimony, Tr. at 486.
43
found in the aisles and the
background. There were no significant concentrations of PCBs in the vicinity of
the quench baths or the machine tool areas where cutting fluids would have been
used.143 According to Eaton's experts, Dr. Lennard Wharton and
Robert Barrick, the nature and dispersion of PCBs reflected the use of PCBs in
capacitors and transformers. They testified that the patchy pattern of limited
PCB contamination consistent with tracking the PCBs from the electrical
equipment areas, and that it was inconsistent with the use of process oils
containing PCBs in open systems such as cutting and quenching operations.144
The MDEQ detected no PCBs in
soil samples taken from the vicinity of the outdoor quench oil storage tanks.145
Neither did the MDEQ find any PCBs in the chip storage area on the southeast
corner of building where one would expect to find them if PCB‑containing
process oils dripped from the metal chips. The closest PCB detection to the
chip storage area was a single detection north of the chip pile at the level of
.53 PPM. 146
Although Monsanto literature describes the use of PCBs in cutting oils, PCB-containing cutting oils did not have widespread or common use. PCBs make a poor additive to cutting fluids because the chlorine in the PCBs is not sufficiently free to assist in the
__________________
143Wharton testimony, Tr. at
370‑88; Barrick testimony, Tr. at 486.
144Wharton testimony, Tr. at
363‑64; Barrick testimony. Tr. at 486‑87.
145Wharton testimony, Tr. at
390; Exh. 6305; Exh. 2085MM.
146Wharton testimony, Tr. at
391‑94, 403; Exh. 6305.
44
cutting process. The
operations at Eaton's Kalamazoo facility did not require anything other than
conventional cutting oils.147
The most commonly used
quench oil in American industry during the 1950s through 1980s was straight
mineral oil. PCB‑containing quench oils were about five times as
expensive as mineral oils. There was nothing about the operations at Eaton's
Kalamazoo plant, such as a risk of fire or ignition of quench oils, that would
militate in favor of using PCBs in quench oil.148
This Court finds that given the relatively low level PCB detections, their concentration around the electrical equipment, the lack of PCB concentrations in the machining and heat treat areas, the lack of PCBs in the area of the chip pile, the fact that PCBs have never been detected as a constituent of the process oils used at the Eaton Kalamazoo facility, and Dr. Brown's concession that the distribution of the PCBs was consistent with leaks from electrical equipment, it is unlikely that the PCBs found at Eaton's Kalamazoo facility were part of the open systems.
Having determined that
Eaton's Kalamazoo facility more likely than not used PCBs in its di‑electric
equipment and in some hydraulic fluid, the Court must still determine whether
the proofs show by a preponderance of the evidence that any of those PCBs found
their way to the Kalamazoo River.
________________
147Wharton testimony, Tr. at
366‑69, 383‑84.
148Wharton testimony, Tr. at
385‑86.
45
On December 7, 2000,
Plaintiff’s expert, Michael McLaughlin, sampled four locations in the vicinity
of the former Eaton facility in Kalamazoo. He sampled two areas, K‑1 and
K‑2, immediately southeast of the plant, as close as he could get to the
location of the chip storage pile without trespassing on Eaton's former
property. He described the location as being just east of the chip pile, and in
the drainage swale between Eaton and the railroad tracks. In sample K‑1
he found Aroclor 1260 at the level of 20 ppb. In sample K‑2, nearby, he
found Aroclor 1260 at the level of 370 ppb.149
Mr. McLaughlin attempted to
test the Zantman Drain in two locations. Sample K‑3, was taken from the
exit of an abandoned concrete culvert under the railroad tracks, a location he
believed was near the outfall from Eaton's plant to the old Zantman Drain. At
this location, almost one‑half mile from the River, he found Aroclor 1254
at the level of 2000 ppb. Based upon the historical documents and his
observations in the field, McLaughlin opined that there were no other sources
for this PCB detection other than the Eaton facility.150
Mr. McLaughlin also sampled
an area north of Mosel Avenue, because he believed that if Eaton discharged
PCBs, they would likely be present in the marshy area described in the
historical documents. He could not
find the marshy area. He did not know if the marshy area had been obliterated
by the 1973 improvements to the Zantman Drain, or
_________________
149McLaughlin testimony, Tr. at
248‑250; Exh. 2085P, Analytical Report prepared for SCS Engineers; Exh.
2085KKK.
150McLaughlin testimony, Tr. at
250‑53; Exh. 2085KKK.
46
whether he just could not
locate it. He took sample K‑4 from a culvert which he believed to be
where the old Zantman Drain went under Mosel. No PCBs were detected at this
location. Mr. McLaughlin now opines that he must have been in the discharge of
the new Zantman Drain.151
Eaton's expert witness,
Robert Barrick, testified that Mr. McLaughlin's detection of low levels of
Aroclor 1260 in the sediments at K‑1 and K‑2, was of little
significance. The 20 ppb detection at K‑1, in particular, was a low
concentration near the detection limits for many routine analyses. The
detection of Aroclor 1260 at K‑1 and K‑2 also failed to match any
of the MDEQ's soil samples from outside of the facility. The MDEQ did not
detect any Aroclor 1260 on the property immediately outside the plant. Aroclor
1254 was the predominant Aroclor
found in the plant. The MDEQ also did not detect any PCBs in the chip storage
area where one would expect to find them if they were in the cutting or quench
oils. Mr. McLaughlin could not account for this discrepancy between his
findings and the findings of the MDEQ. The area the samples were taken from
could have included material from many places other than Eaton, including
upstream sources on the Zantman Drain, or the highway. According to Mr.
Barrick, in light of this negative and contradictory evidence, it would not be
reasonable from a scientific standpoint to associate the PCB detections at K-1
and K‑2 with the Eaton facility. 152
_________________
151McLaughlin, testimony, Tr.
at 254‑56.
152Barrick testimony, Tr. at
501‑03.
47
Mr. Barrick acknowledged
that the PCBs in sample K‑3 could be associated with the Eaton facility,
although there is also the possibility that it could have come from another
source, such as the railroad tracks. Mr. McLaughlin acknowledged that there was
runoff from the railroad tracks, and that there are reports of PCB
contamination associated with
railroad tracks. He stated, however, that PCBs were not generally on collector
lines like the one at issue, but were rather associated with maintenance
facilities and electric locomotives. 153
According to Mr. Barrick,
the non‑detection of PCBs at K‑4 is of particular significance.
Even assuming K‑4 was taken where the new Zantman Drain emerges from
under Mosel Avenue, rather than where the old Zantman Drain used to emerge, it
would have been one of the first collection points for sediment or other oil
from the plant. Because this is a slow‑moving, organic‑rich system
with a lot of vegetation, it would have absorbed many of the PCBs if they had
been present. Accordingly, if PCBs had been used in the cutting oils or in the
heat treat areas of the plant, the plant would have been a continuing source of
PCBs, and one would expect to find them in the culvert.154 The lack
of PCBs at K‑4 tends to indicate that PCBs were not a part of the process
oils used in the open systems at the Eaton Kalamazoo facility.
________________________
153McLaughlin testimony, Tr. at
252‑53.
154Barrick testimony, Tr. at
505‑08.
48
Mr. Barrick testified that
the PCBs found on the floor at the Kalamazoo facility related to incidental leaks
from the electrical equipment. Very little contamination left the facility, and
what contamination did leave was
sporadic. According to him, such incidental PCBs would tend to be trapped in
the marshy area north of Mosel Avenue, and would not have made it all the way
down the drain to the Kalamazoo River.155
KRSG did no testing for PCBs
between Mosel Avenue and the River. Eaton contends that Plaintiff’s failure to
do so is a fatal flaw in its proofs in this two site case. The Sixth Circuit
previously observed in Benteler that
In a two‑site case such as this, where hazardous substances are released at one site and allegedly travel to a second site, in order to make out a prima facie case, the plaintiff must establish a causal connection between the defendant's release of hazardous substances and the plaintiffs response costs incurred in cleaning them up.
Benteler, 171 F.3d at 1068. This
Court's entry of summary judgment in favor of Benteler was affirmed in light of
evidence that the drainage ditch that allegedly connected Benteler to Morrow
Lake and the Kalamazoo River was 3200 feet long the evidence was unrefuted that
no PCBs were detected beyond 1500 feet from the facility; hydrogeological
evidence demonstrated that the ditch lacked sufficient water flow to carry PCBs
the full length of the ditch; and soil and vegetation in the ditch was not
consistent even with occasional discharges of sufficient magnitude to carry
water down the ditch to Morrow Lake. Id.
at 1068‑69.
__________________
155Barrick testimony, Tr. at 488‑89.
49
The evidence with respect to
the lack of flow through Zantman Drain is not as strong as the evidence with
respect to the drain at issue in Benteler.
In this case, while the drainage was slow, there did appear to be
sufficient water flow to connect the Zantman Drain with the Kalamazoo River. In
light of the evidence that PCBs were found on the floor at Eaton's Kalamazoo
facility, that Eaton was discharging almost half a million gallons of
wastewater to the Zantman Drain on a daily basis in 1965 and 1968, and that
there was at least a trickle of water coming through the drain pipe from under
the Upjohn Building at this time, the Court is satisfied that there was some
flow from Eaton to the Kalamazoo River via the Zantman Drain.
Plaintiff's expert, Dr.
Brown, undertook some sampling of the Kalamazoo River upstream and downstream
of the Eaton Kalamazoo facility in an attempt to isolate the potential effect
of the Zantman Drain. He testified that based upon the wide variability in the
samples, both as to concentration and composition of Aroclors, he could not
prove or disprove a release of PCBs from Eaton's Kalamazoo facility. The
release of PCBs from Eaton would have to increase the concentration of River
PCBs by almost fifty percent before they would be detectable. Even when he
adjusted concentrations by dividing by the amount of organic matter, there was
still too much scatter in the data to show any contribution from Eaton's
Kalamazoo facility. Dr. Brown explained that because the twenty mile segment of
the River from the foot of the Morrow Dam upstream of the Kalamazoo facility,
all the way down to Plainwell, has no dams or obstacles, and is fairly steep
and fast‑ flowing, it operates
50
as a pipe, moving the PCBs
downstream to Lake Allegan. According to Dr. Brown, while it is not possible to
trace the PCB detections in the River to Eaton or to any other source along the
Kalamazoo River, the detections are consistent with a PCB discharge from
Eaton's Kalamazoo facility. Dr. Brown opined that PCBs were released from the
Kalamazoo facility in oils to the Zantman Drain and the Zantman Drain
transported those to the Kalamazoo River. 156
Eaton's expert, Mr. Barrick,
also studied the Kalamazoo River in the vicinity of the Zantman Drain. He
agreed with Dr. Brown that the Kalamazoo River in the vicinity of the Zantman
Drain is relatively straight. However, he indicated that just before the
Zantman Drain, the River makes a loop going left and right. This meander
results in slower flow and provides opportunities for material to collect. Even
if the River in this vicinity is characterized as a pipe, it is a rough pipe
with many pockets for material to accumulate.157
Mr. Barrick studied hundreds of samples from the River collected by the MDEQ and by BBL on behalf of KRSG. Rather than stepping back and averaging the samples for a broad view, he took a more forensic approach and focused on individual samples and specific Aroclors to determine whether the Zantman Drain was a potential source of PCBs to the River. Because he found no increase in 1254/1260 (the Aroclors found at the Eaton plant), that was not accompanied by a rise in other Aroclors that could not be attributed to
_______________
156Brown testimony, Tr. at 150‑59; Exh. 2086A,
Map of Kalamazoo River in Vicinity of Eaton Corporation's Kalamazoo Facility.
157Barrick testimony, Tr. at 511‑12, 527‑28
; Exh. 6306, Facility Location.
51
Eaton, he concluded that there was no correlation between the
Zantman Drain and the River sediments. When he focused on the samples with the
highest percentage of Aroclors 1254 and 1260, he found that there were more of
these samples upstream of Eaton than downstream. There was nothing atypical,
unusual or remarkable downstream of the Zantman Drain that was not already
apparent in the system upstream.158 Based upon the data from the
facility, the drain and the River, Mr. Barrick concluded that the most logical
interpretation is that there was no contribution of PCBs from the Eaton
Kalamazoo facility.159
In determining whether Eaton's Kalamazoo facility is liable for the release of PCBs to the River the Court has considered all the evidence presented. The Court notes that there is no testimony from anyone with personal knowledge that Eaton ever used PCB‑containing oils in its processes. There is no evidence of any test results showing the presence of PCBs in the cutting oils or quench oils used in the Eaton plant. There is no testimony that Eaton engaged in activities that required PCB additives in the cutting or quench oil. PCBs were, however, found on the floors of the facility. Although Aroclor 1248 was detected in only one sample, its presence makes it more likely than not that Eaton used PCB‑containing hydraulic oil at some point in time. It is also more likely than not that some of Eaton's capacitors and transformers leaked PCB‑containing oil. Eaton's oils and waste discharges
________________________
158Barrick testimony, Tr. at 513‑21; Exh. 6307,
Proportions of Aroclor 1254 and 1260 in total PCBs from confluence to KPT‑39.
159Barrick testimony, Tr. at 529.
52
were reported throughout the
length of the Zantman Drain, north of Mosel Avenue, as reflected in numerous
complaints and reports in the historical record. Based upon all the evidence
and the Sixth Circuit's direction that any release of PCBs is sufficient for a
finding of liability, the Court finds it more probable than not that some of
the PCBs from the floor of the Kalamazoo facility were washed down the drain
and into the Kalamazoo River along with the other oily wastes from the
facility. The Court accordingly concludes that Eaton's Kalamazoo facility is
liable for the release of some PCBs to the Kalamazoo River.
IV. MARSHALL FACILITY
Of the three Eaton
facilities at issue in this case, the Marshall facility is located farthest
upstream. The Marshall facility is thirty miles upstream of the NPL Site, but
is within the area to be studied under the AOC. The Marshall facility is
approximately one-quarter mile from the Kalamazoo River.
Eaton has operated the Marshall
facility since 1941.160 Historically, the Marshall facility was
engaged in the manufacture, assembly and testing of hydrostatic transmissions,
viscous fan clutches, power steering pumps, differentials and lubricating oil
pumps. Machining operations included lathing, grinding, boring and drilling.
There were no forging operations at the plant, but some of the parts received
heat treatment.161 In contrast to the Battle Creek and Kalamazoo
facilities, the Marshall facility is still in operation.
_________________
160Fesko dep. at 39‑40;
Olof Stolen dep. at 188‑89.
161Stolen dep. at 10, 17‑18,
45‑46.
53
No evidence was presented of
any use of PCB‑containing oils in the processes at the Marshall facility.
There was no testing of the process oils at the Marshall plant showing the
presence of PCBs, and no Eaton employee has testified to the use of PCBs in the
process oils at the Marshall plant. 162
Although some of the
electrical equipment at Eaton's Marshall plant used PCB-containing oils,
Plaintiffs presented no evidence of any leaks at the Marshall facility from
these closed systems. Thomas Swalwell has been employed at Eaton's Marshall
facility for thirty‑one years, since 1966, as an electrician and
maintenance supervisor. He testified that there were trays under all of the
capacitors to catch any leaks, but he was not aware of any capacitor ever
leaking at the Marshall facility.163
The wastewater from the
Marshall plant was sampled and tested for PCBs by the MDNR in 1973. No
detectable levels of PCBs were found. 164 The wastewater from the
Marshall plant was sampled and tested for PCBs by the MDNR again in August
1980. Testing was done at two outfalls from the plant to the storm sewer.
Cooling waters, roof and yard drainage were discharged through Outfall 001.
Cooling water used in degreasers, heat exchangers and welders was discharged to
Outfall 002. The MDNR reported that PCBs had been detected at Outfall 001 at
the level of 0.82 ug/1 (ppb). No detectable levels of PCBs
________________
162Brown testimony, Tr. at 171.
163 Thomas Swalwell dep. at 4‑6,
112‑13.
164Exh. 6105, 8/6/73, letter
from MDNR with Report of 6/12/73‑6/14/73 Industrial Wastewater Survey.
54
were found at Outfall 002.165
The MDNR suggested that the PCBs that were found "are most likely associated
with the oils that are used at the plant," and recommended that Eaton test
the oils at the plant for PCBs to determine the exact source and to eliminate
these toxic compounds from the discharge. 166
Eaton immediately followed
up on the MDNR's 1980 detection of PCBs at Outfall 001. A review of all
incoming products disclosed none containing PCBs. 167 Eaton also
took additional samples of wastewater at Outfalls 001 and 002, and a
concentration of water soluble oil and machinery fluid, on January 9, 1981. The
samples were sent to Environmental Research Group, Inc. All samples were non‑detect
for PCBs.168
The 1980 PCB detection has never been repeated, despite additional sampling. On April 3, 1981, Thomas Newell of the MDNR recommended that PCB monitoring should no longer be required at Eaton's Marshall facility "because they do not use it." Newell stated that is was his "opinion that occasional PCB's may be in the oils used in the plant but at trace contaminant levels.169 Further sampling in 1983 of pollutants in the Marshall facility
_____________________
165Exh. 6101, MDNR letter of
12/18/80 with Report of Industrial Wastewater Survey.
166Exh. 6101, 12/18/80 letter
at 2.
167Exh. 6103, Rex Simmons, Mng.
Plant Engineering 1/26/81 letter to MDNR.
168Exh. 6102, ERG Amended
Laboratory Analysis report dated 1/26/81.
169Exh. 6104, Newell Memorandum
of 4/3/81.
55
wastewater was also non‑detect
for PCBs.170 On November 21, 1985, the MDNR conducted an inspection
to determine compliance with PCB regulations. The inspection revealed no
leaking transformers or capacitors. Company officials reported no known use of
Pydraul in their hydraulic systems. All testing of plant oils was non‑detect
for PCBs.171
Eaton's Marshall plant
dumped industrial wastes in a
landfill from the 1950s to the 1970s. In 1990 the USEPA conducted an inspection
of the Eaton landfill in Marshall. There is no reference in the report to any
PCBs.172
In 1993, Eaton engaged an
outside environmental consultant, Applied Science and Technology, Inc. ("ASTI"),
to conduct sediment sampling for PCBs in the Kalamazoo River immediately
downstream of the Marshall facility. The purpose of the testing was to
determine whether PCBs had been discharged from the Marshall plant. Because
PCBs have an affinity for fine‑grained sediments if they were to settle
out, the consultants tested fine-grained sediments from the three depositional
zones identified. No detectable levels of PCBs were found.173
__________________
170Exh. 6101, MDNR letter of 1/17/84, with Report of 5/983‑5/10/83
Industrial Wastewater Survey; Exh. 6107, 3/20/84 letter from Eaton to MDNR,
with 1/30/84 lab results of 12/23/83 samples.
171Exh. 6108, MDNR 11/21/85 Report on PCB Inspection,
at 4.
172Exh. 6109, MDNR 8/1/90 Screening Site Inspection
Report for Eaton Landfill.
173Exh. 6111, ASTI 5/14/93. Sediment Sampling; Brown
testimony, Tr. at 177‑78.
56
No one on behalf of
Plaintiff has tested the sediments in the vicinity of Marshall and immediately
downstream of the Marshall facility. KRSG has conducted no testing of River
sediments between the Marshall plant and Morrow Lake,174
approximately thirty miles downstream of the Marshall plant.175
The studies that have been
conducted in the River between Marshall and Morrow Lake reveal no PCBs in the
vicinity of the Marshall plant. In 1976 and 1988 the MDNR sampled riverbed
sediments in impoundment areas downstream of the Eaton Marshall plant, where
PCBs would be expected to be deposited, and found none.176 In all
the sampling of riverbed sediments and settleable solids for almost twenty
miles downstream of Marshall, no PCBs were detected.
Plaintiff's entire case
against Eaton's Marshall facility rests upon the single detection of PCBs in
the MDNR's 1980 water survey. Dr. Brown testified that although non‑detects
are not sufficient in and of themselves to rule out the presence of PCBs at a
site, a single detection of PCBs is typically good confirmation that PCBs were
present.177
Although one discharge may be sufficient to support a finding of liability, this Court looks for some corroborating evidence to insure that the one detection is reliable. In this
_______________
174Connolly testimony, Tr. at
481.
175Brown testimony, Tr. at 178.
176Exh. 2036/6110, Wuycheck
Study; Exh. 6020, 1988 study.
177Brown testimony, Tr. at 166.
57
case there is no
corroborating evidence. Eaton went to great lengths to determine the possible
source of the PCBs, and was not able to find any. Despite repeated efforts,
Eaton has never been able to replicate the MDNR's finding.
Thomas Newell, MDNR District
Engineer, testified that it was his opinion that the Marshall plant's PCB
detection was due to PCB containing process oils commonly used in the auto
parts manufacturing industry. His opinion amounts to no more than speculation.
He had no personal knowledge of the oils Eaton actually used at the plant. In
fact, his opinion was based in part on his assumption that Eaton had a die‑casting
operation.178 This assumption was inaccurate, as Eaton did not
conduct die‑casting at its Marshall facility.179
The KRSG has done nothing to
verify the reliability of the one PCB detection. Dr. Brown has no specific
knowledge of the application of PCBs in cutting oils at the Marshall plant.180
Despite the fact that the Eaton Marshall facility is still in operation, and
despite the fact that Eaton's historic wastes are known to be present at the
Eaton landfill in Marshall, no showing has been made that KRSG made any effort
to collect evidence from these obvious sources of historic information.
Based upon all the evidence
presented, the Court finds that the single admittedly low level detection of
PCBs at the Marshall facility in 1980 is not reliable. There being no other
_______________
178Newell dep. at 45.
179Brown testimony, Tr. at 169.
180Brown testimony, Tr. at 170.
58
evidence of PCBs discharged
by the Marshall facility, the Court concludes that Plaintiff has not met its
burden of demonstrating by a preponderance of the evidence that Eaton released
PCBs from its Marshall facility to the Kalamazoo River. Accordingly, the Court
finds that Eaton is not liable for the release of any PCBs from its Marshall
facility.
In summary, the Court finds
that Eaton is liable for the release of PCBs in some quantity, small though it
may have been, from its Battle Creek and Kalamazoo facilities, but that Eaton
is not liable for the release of PCBs from its Marshall facility.
An order and partial
judgment as to liability consistent with this opinion will be entered.
Date: May 9, 2001
ROBERT HOLMES BELL
UNITED STATES DISTRICT JUDGE
59
UNITED STATES DISTRICT COURT
FOR THE WESTERN DISTRICT OF
MICHIGAN
SOUTHERN DIVISION
|
KALAMAZOO RIVER STUDY GROUP, |
|
|
Plaintiff, |
File No. 1:95‑CV‑838 |
|
v. EATON CORPORATION, |
HON.
ROBERT HOLMES BELL |
|
Defendant. |
|
In accordance with the
opinion entered this date,
IT IS HEREBY ORDERED that JUDGMENT
AS TO LIABILITY ONLY is entered in favor of Plaintiff Kalamazoo River Study
Group and against Defendant Eaton Corporation with respect to Eaton
Corporation's Battle Creek and Kalamazoo facilities.
IT IS FURTHER ORDERED that JUDGMENT
is entered in favor of Defendant Eaton Corporation with respect to its Marshall
facility.
Date: May 9, 2001
ROBERT HOLMES BELL
UNITED STATES DISTRICT JUDGE